The biggest flood project Charleston has ever tried just got real money, and it's being designed to look like a park. Whether you'll be allowed to ride a bike on it is still an open question.
It's called the Battery Extension. The city and the U.S. Army Corps of Engineers plan to stretch the High and Low Battery around much of the peninsula, with a public promenade on top. Total price is about $1.3 billion. The city's share is about $455 million, and the federal government covers 65%.
On Nov. 3, Charleston County voters passed the transportation sales tax by more than 60%. About $225 million of it is set aside for the Battery Extension.
The design work is already paid for. The Corps awarded $6.2 million to a Stantec-JMT team in North Charleston. About $2.9 million covers Adgers Wharf, roughly 1,000 feet on the east side from East Bay Street to the south end of Waterfront Park. About $3.3 million covers the Lockwood Drive stretch along the Ashley River, around 8,000 feet, which protects the Medical District. Expect survey crews and soil borings over the next few months. Early phases are penciled in for 2027 to 2031, depending on funding.
Bikes are the sticking point. The city already ditched a plain concrete wall for a continuous path you can walk. Walking is the plan. Riding is a different story.
The Post & Courier reports that bikes and e-bikes are already banned on the High and Low Battery, and that the city's planning document for the extension mentions bikes once. Katie Zimmerman, who runs the bike and pedestrian group Charleston Moves, told the paper she doesn't expect cyclists to be welcome on the new wall, and that she's OK with it. Her group is spending its energy on Lockwood, Broad Street and dangerous intersections instead.
The one bright spot is on the west side. A city spokesperson told the paper the goal is to connect the Lockwood stretch to the Ashley River Crossing, the bike and pedestrian bridge to West Ashley that's under construction now. Details are still to come.
Two more data points. In May, the city banned e-bikes from every sidewalk, while keeping them legal in bike lanes and on multi-use paths. And when County Council voted on whether to add bike and pedestrian language to the sales tax ballot, it failed 5-4.
To see what the finished product might feel like, walk the Low Battery. The seawall repair there wrapped up in February after more than 11 years of work. Leave the bike at home.
Sources: the City of Charleston (project design, partners) and its Ashley River Crossing page, the U.S. Army Corps of Engineers (cost share, schedule), ABC News 4 (design contracts), Live 5 News (segment lengths), ABC News 4 (tax vote), the Charleston City Paper on project cost and e-bike rules and the ballot, JMT (Low Battery completion) and the Post & Courier (current bike ban, planning document, Charleston Moves, city spokesperson)